Business Case Updates at Each Stage—How Often
Posté 2025-11-10 13:16:07
0
85
In PRINCE2, the Business Case is the North Star: it answers “Is this project still worth doing?” Because viability can drift, PRINCE2 mandates regular, event-driven checks—not a “set-and-forget” document.
Ownership & Accountability
- Accountable: Executive (Project Board).
- Responsible for maintenance: Project Manager (on behalf of the Executive).
- Assurance: Senior User validates benefits; Senior Supplier validates feasibility/costs; Project Assurance challenges assumptions.
Minimum Cadence (PRINCE2-compliant)
- Project Initiation (PID approval):
Create/confirm the Business Case and Benefits Management Approach. - End of Every Stage (Managing a Stage Boundary):
Formal review and update before the next Stage Plan is approved. The Project Board re-confirms continued business justification. - Exception Situations (Exception Assessment):
Immediate review if forecast breaches tolerances (time/cost/quality/scope/benefit/risk). Approve an Exception Plan only if the updated case still stacks up. - Benefits Reviews (Post-Project):
Conduct benefits realization reviews per the Benefits Management Approach (e.g., T+3 months, T+6 months, T+12 months after go-live).
If nothing material changes within a stage, the Business Case can remain stable until the next end-stage review.
Materiality Thresholds (good practice):
- Cost: ±10% stage EAC variance or any change > the project cost tolerance.
- Schedule: Slippage > 10% of stage duration or impacts benefits window.
- Benefits: ≥5% downside to year-1 benefits or deferral of key benefit beyond payback horizon.
- Risk: Exposure (P×I) increases by one risk band (e.g., Medium → High).
- Scope: Change to MVP/critical product descriptions affecting benefits realization.
When a threshold is exceeded, update Business Case immediately and, if viability weakens, escalate to the Project Board.
What Exactly to Update
- Financials: Revised CAPEX/OPEX, NPV, IRR, Payback period.
- Assumptions & Dependencies: New lead-times, vendor constraints, regulatory shifts.
- Benefits Profile: Timing, magnitude, measurability; confirm owners.
- Risk Exposure: Top threats/opportunities and mitigations; residual risk.
- Options Analysis: “Do nothing / Do minimum / Do something” comparison refreshed.
- Sensitivity & Scenario Testing: Best/base/worst case with clear triggers.
Stage-by-Stage Playbook
Start-Up & Initiation
- Draft outline Business Case → evolve to a full Business Case in the PID.
- Lock the Benefits Management Approach (who measures what and when).
Stage 1…N (Delivery Stages)
- During the stage: scan Highlight Reports; if thresholds trip, update now.
- End of stage: run End Stage Report + refreshed Business Case; Board decides “Continue / Change / Stop.”
Final Delivery Stage
- Confirm benefits that can be measured at project closure; schedule the rest post-project.
- Hand off the Benefits Management Approach to Operations/Benefits Owner.
Post-Project
- Execute benefits reviews on the agreed dates; update the Business Case record with actuals vs forecast; capture lessons.
Rechercher
Werbung
Catégories
- Cars & Motorsport
- Art
- Causes
- Crafts
- Dance
- Drinks
- Film
- Fitness
- Food
- Jeux
- Gardening
- Health
- Domicile
- Literature
- Music
- Networking
- Autre
- Party
- Religion
- Shopping
- Sports
- Theater
- Wellness
- IT, Cloud, Software and Technology
Lire la suite
Code Promo Gratuit : Ce Qu'il Faut Savoir Avant l'Activation
Les codes promo, les codes bonus et les offres promotionnelles sont devenus des...
Building Strong Foundations Through a Progressive School
Choosing the right school can influence a child's academic habits, confidence,...
Wholesale Artificial Wedding Flowers & Custom Floral Arrangements | Yongnuo Flower
Discover high-quality wholesale artificial wedding flowers and custom floral arrangements from...
Common eCommerce Development Mistakes and How to Avoid Them
Opening an online store involves more than just adding products, creating payment systems, and...
What Makes A2 Butter Better Than A1?
A2 butter stands out compared to A1 thanks to its rich nutritional profile, providing...